Environmental: Prepared the environmental and social impact assessment for the solar power plant and the transmission line in compliance with the requirements of the Lesotho EIA Act 10 of 2008 as well as international best practices - IFC PS on environmental and social sustainability.
Engineering: Site layout and assessment, review of PV panel and mounting structures.
Environmental: Development of Environmental and Social Management System (ESMS) Manual to guide ZETDC operations to comply with national, regional and international environmental and social standards.
Training: Managing environmental and social risks associated with operations.
Engineering: Conceptual design review and construction project management
Professional engineers working with Citseo Consulting provided engineering and project management services to a province owned hydropower project. Worked with Project Director and Engineering team to deliver project status reporting updates and ensured that change, acceptance and approval management is proactive
Developed environmental criteria during conceptual design, coordinated environmental and social impact assessment study from planning to execution, and preparation of environmental and social impact assessment report.
Our professionals carried out scoping study, described and analyzed the environmental and social context in which the project operates., identified the impact of the planned upgrade, and prepared the ESIA report
Professional engineer working with Citseo Consulting developed schedule for construction work package, coordinated the development of recovery plan with project team, monitored and prepared change management plan and monitored project productivity.
Our professionals carried out scoping study, described and analyzed the environmental and social context in which the project operates., identified the impact of the planned upgrade, and prepared the ESIA report
Construction Monitoring. Prepared the environmental and social management and monitoring plan for construction activities at Butha Buthe, Mohale’sHoek, Hlotse and Mafeteng
Managed and monitored construction activities to ensure contractors compliance with the management plans developed for the project and the national regulatory requirements.
Our professionals carried out scoping study, described and analyzed the environmental and social context in which the project operates., identified the impact of the planned upgrade, and prepared the ESIA report
Environmental and Social Impact Assessment: Coordinated multidisciplinary team, conducted socioeconomic and environmental field data collection, and prepared the environmental and social impact assessment (ESIA) for the uptake infrastructure, WTP and the distribution lines.
Stakeholder Engagement: Identified and analyzed stakeholders, stakeholder planning, developed engagement strategy and plan, developed stakeholder engagement plan and coordinated stakeholder engagement
RAP: Our professionals developed a resettlement action plan that specify all resettlement arrangements and the measures for avoiding, minimize and compensation of losses or other negative social impacts resulting from the resettlement.
LRP: We developed livelihood restoration plan that provides guiding principles and procedures that will be followed in managing the impacts of the neighborhood upgrade on the project affected persons economically displaced by the project
Stakeholder Engagement: We engaged with stakeholders throughout the project cycle. We identified , analyzed, plan, developed strategy and communicate project information to interested and affected person and received feedback.
Our professionals developed an environmental and social scoping report which sets out the proposed scope of the ESIA, including surveys or data gathering to be carried out as part of the baseline assessment, the approach to be taken in conducting the assessment, and the basis for identifying the mitigation measures required to avoid, reduce or offset the identified potentially significant environmental effects of the development.
Stakeholder Engagement: We engaged with stakeholders throughout the scoping phase. We identified , analyzed, plan, developed strategy and communicate project information to interested and affected person and received feedback.